Sprint Analytics · November 5, 2026 · 5 min read · By Henry Sword

How to Track Committed vs Delivered Work for Each Sprint in Azure DevOps

One completion percentage hides too much. Track committed, delivered and carryover separately, with one rule that means the same thing every sprint.

  • #committed vs delivered
  • #sprint carryover
  • #commitment reliability
  • #sprint reporting
  • #azure devops
  • #scrum

For each finished sprint, track three numbers: what the team committed to, what it delivered, and what carried over, with each counted by one fixed rule so it means the same thing every sprint. In Azure DevOps, the Agile Analytics extension reports these per team in Sprint Summary.

Three numbers, not one

A single completion percentage hides too much, so keep these separate.

  • Delivered of committed. Did the team finish what it said it would? Sprint Summary reports this as commitment reliability.
  • Done of all items. How much of everything that ended up in the sprint got finished, including work added after planning?
  • Carryover. How much unfinished work stayed in the sprint at the end, or moved straight into the next one?

When the commitment is locked

Committed means what is in the sprint at the end of its first day, measured in UTC. Sprint Summary shows this as Planned Items, "Committed at end of day 1", and anything added later appears under Scope Change. So plan before the end of day 1. A team that plans the day before the sprint starts is covered. A team that moves its stories in on day 2 will see 0 planned and all of them as added.

What counts as carryover

An item is carryover for a finished sprint when all three of these are true.

  1. It was in the sprint at the end of at least one sprint day.
  2. It was not done when the sprint ended or when it left the sprint. Done means the first state mapped as Done in Workflow Mapping, with one day of grace after the last sprint day.
  3. It was either still in the sprint at the end, or moved straight into the next sprint.

And what does not

Three edge cases decide most arguments.

  • Moved back to the backlog unfinished: removed scope, not carryover.
  • Pulled in by mistake and out the same day: never counts.
  • Late additions: they count, and the view says so ("2 added in the last 2 days"), so a spike from late scope is visible.

Why a backlog move is removed scope

Rolling an item into the next sprint means the team still intends to work on it now. Sending it back to the backlog is a decision to stop for the time being. Counting both as carryover would penalise a team for descoping honestly, and reward quietly leaving items in the sprint. Scope change is reported separately, so descoping stays visible.

Related: Reducing sprint carryover without gaming it

How the percentage works

Carryover percentage is carryover divided by every item in the sprint at the end of at least one day. It does not need a commitment, so teams that never lock one still get a figure. A running sprint shows a dash ("Carryover is counted when the sprint ends."), because mid-sprint it would only be a count of unfinished work.

Related: How carryover is counted

Get the Done line right first

Every number here depends on where done sits in your process. If Ready to Release is mapped as Done, items count as delivered when they reach it. An admin can check this under Tools, Configuration, Workflow Mapping.

Related: Workflow Mapping for accurate analytics

Reading several sprints

One sprint is an anecdote. Sprint Velocity, a Dashboard card that is off by default, shows the last 6 sprints, and Delivery Signals shows the reliability and carryover trend for one team. The running sprint never enters an average. If carryover holds while delivered of committed drops, the team is probably overcommitting. If carryover rises with late additions, look at what enters the sprint.

Comparing several teams

With two or more teams selected, Sprint Summary shows Teams at a glance: delivered of committed, done of all items, scope change and carryover. For a parent team, the Sub-teams view has a Delivery tab with the same ideas per sub-team. Nothing rolls up across Azure DevOps organisations.

Related: How to roll up sub-teams to a parent team

Where the rule applies

Sprint Summary, Sub-teams, Sprint Velocity, the Dashboard, Delivery Signals, Exec Report and AGAN AI all use this carryover rule. Team Benchmarks, Retro Snapshot and the Team Health widget do not yet: they still count committed items not finished by sprint end, so their figures can differ.

Try it

Agile Analytics runs on Azure DevOps Services (cloud). The 30-day free trial starts on install with no credit card, and everyone in the organisation has full access while it runs.

Related: Sprint reports: scope and carryover · Install instructions

Compare your Azure DevOps reporting options before you commit

See how built-in ADO reporting, Power BI, and Marketplace extensions stack up, then start the 30-day trial to evaluate the extension path inside your own organisation.

Related reading

Find our articles faster: add Agile Analytics as a preferred source in Google Search.Add preferred source →